Resources and Procurement
PMP PMP · Process
Resources: getting the right people and things
Resource management covers everything the project needs to do its work: people, equipment, materials, facilities, and supplies. The July 2026 ECO gives the Process domain two tasks here: plan and manage resources, and plan and manage procurement. For people, the work starts with estimating what the project needs — which skills, how many people, and when — and recording it in a resource management plan. Then the project manager acquires the resources, which in a matrix organization usually means negotiating with functional managers who control the people, rather than hiring directly. The exam tests this negotiation constantly: the project manager who needs a specialist for three weeks must negotiate with the functional manager who also needs that specialist, and the correct approach is collaboration — understanding the functional manager's constraints and finding a schedule that works for both — not escalation or demands.
Resource planning also covers physical resources: equipment, materials, and facilities. The exam expects you to think about availability, lead times, and logistics — ordering materials with long lead times early, scheduling shared equipment so it is available when needed, and planning for the storage and handling of physical deliverables. In practice questions, physical resource problems often appear as schedule problems: a project delayed because a key piece of equipment was not booked in time is a resource management failure, and the fix is in planning, not in crashing the schedule afterward.
Managing the team as a resource
Once acquired, team resources must be developed and managed — which overlaps with the People domain's team leadership work. From the Process side, the key ideas are the resource breakdown structure (RBS), which organizes resources by category and type, and the responsibility assignment matrix (RAM), which maps work packages to the people responsible for them. The best-known RAM is the RACI chart: for each activity, one person is Responsible (does the work), one person is Accountable (owns the outcome — and there should be exactly one), some are Consulted (give input before the decision), and some are Informed (told after the decision). The exam tests RACI directly: a question describing confusion about who owns a decision is usually a RACI problem, and the fix is to clarify the single accountable person.
Resource management also includes recognizing and rewarding the team, managing resource calendars (when each resource is available), and controlling resources — monitoring usage against the plan and taking corrective action when resources are over- or under-used. Over-allocation is the most common resource problem on the exam, and the fixes are the ones covered in the schedule guide: resource leveling (which can extend the schedule) and resource smoothing (which works within float).
Procurement: buying what the project needs
Procurement management covers acquiring goods and services from outside the project — from a single piece of equipment to a multi-year outsourcing contract. The first decision is make-or-buy: should the project produce something itself, or buy it from a seller? The analysis weighs cost, capability, control, risk, and strategic importance. The exam tests make-or-buy through scenarios: a project that needs a specialized component it has never built before, with a seller who can deliver it faster and cheaper, should usually buy; a component that is core to the organization's competitive advantage should usually be made in-house, even if buying is cheaper.
Once the decision is to buy, the project manager (often with a procurement department) prepares procurement documents — a statement of work describing what is needed, and the terms and conditions — and selects a seller through a process that the exam calls conduct procurements. Seller selection uses criteria that go beyond price: technical capability, past performance, financial stability, and references all matter. The exam's rule is that the lowest bid is not automatically the best bid — a suspiciously low price may signal a seller who does not understand the work, and selecting on price alone is a common exam trap.
Contract types: who bears the risk?
Contract types are one of the most tested procurement topics, and the key question is always the same: who bears the cost risk — the buyer or the seller? There are three families:
| Contract family | Who bears the cost risk? | When it fits |
|---|---|---|
| Fixed-price (FP, lump sum) | The seller. The price is agreed up front; if costs rise, the seller absorbs them. | Well-defined scope, stable requirements. The buyer knows the total cost in advance. |
| Cost-reimbursable (CR, cost-plus) | The buyer. The seller is reimbursed for actual costs plus a fee; if costs rise, the buyer pays. | Uncertain scope, where the seller cannot reasonably price the work in advance. |
| Time and materials (T&M) | Shared. The buyer pays an agreed rate for time and materials used. | Small, short efforts, or when the scope cannot be fully defined but the work is straightforward. |
Within fixed-price contracts, the common variants are firm fixed price (FFP — one price, no adjustment) and fixed price incentive fee (FPIF — a target price plus an incentive for beating cost or schedule targets, with a price ceiling). Within cost-reimbursable contracts, the variants differ in how the fee is calculated: cost plus fixed fee (CPFF — a fixed fee regardless of cost), cost plus incentive fee (CPIF — the fee varies with performance against a target cost), and cost plus award fee (CPAF — a fee awarded subjectively based on performance). The exam tests these mainly by asking which contract type fits a scenario, or who bears the risk in a given contract. The pattern to remember: the more uncertain the scope, the more the risk shifts to the buyer; the more certain the scope, the more the seller can accept a fixed price.
Two more contract concepts appear on the exam. A point of total assumption (PTA) applies to FPIF contracts: the cost level at which the seller bears all further cost increases, because the price ceiling has been reached. And contract change control is the process for changing a contract: changes must be agreed in writing by both parties — a verbal agreement to change the scope of a contract is not binding, and the exam will test this with a scenario where a seller claims extra payment for work the buyer never formally approved.
Controlling procurements
Once a contract is in place, the project manager controls procurements: monitoring the seller's performance against the contract, managing the relationship, handling changes, and ensuring both sides meet their obligations. This includes inspections and audits of the seller's deliverables, performance reviews, and payment management. The exam tests this through scenarios where a seller is underperforming: the correct response is to review the contract terms, discuss the performance issue with the seller, and work toward a resolution — not to withhold payment unilaterally (which may breach the contract) or to terminate the contract as a first step.
Closing procurements means verifying that all work is complete, all deliverables are accepted, all payments are made, and any disputes are resolved — and then formally closing the contract. Procurement closure happens before or as part of project closure, and the exam expects you to know that a contract is not closed until all obligations on both sides are fulfilled.
Exam mindset for resources and procurement
For resource questions, think negotiation and clarity: negotiate for people collaboratively, clarify roles with RACI, and fix over-allocation with leveling or smoothing. For procurement questions, think risk: who bears the cost risk in this contract type, and does the contract fit the certainty of the scope? And remember that the lowest bid is not automatically the best, that contract changes must be in writing, and that seller problems are resolved through discussion and the contract terms — not through unilateral action.
Exam traps to watch for
- Selecting the lowest bidder automatically. Price is one criterion among many — a suspiciously low bid may signal a seller who does not understand the work.
- Confusing who bears the risk: in fixed-price contracts the seller bears the cost risk; in cost-reimbursable contracts the buyer does.
- Having more than one person accountable in a RACI chart. There is exactly one Accountable person per activity; several people can be Responsible, Consulted, or Informed.
- Accepting verbal contract changes. Contract changes must be agreed in writing by both parties; verbal agreements are not binding.
Practice questions
Test yourself on this guide. Answers are checked instantly, with a full explanation for each question.
Q1.A project needs a specialized component. The scope is well defined, the requirements are stable, and several sellers can supply it. Which contract type is MOST appropriate?
Explanation: When scope is well defined and requirements are stable, the seller can price the work accurately, so a firm fixed price contract is appropriate: the buyer knows the total cost in advance and the seller bears the cost risk. Option A is wrong because cost-reimbursable contracts are for uncertain scope — here the scope is certain, so there is no reason for the buyer to bear the cost risk. Option B is wrong because T&M is for small, short efforts or work that cannot be fully defined; it leaves the total cost open-ended when a fixed price was available. Option D is wrong because CPAF is a cost-reimbursable contract with a subjective award fee — again, the wrong risk allocation for well-defined scope.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q2.A project's scope is highly uncertain and the seller cannot reasonably estimate the total cost of the work. The buyer still needs the work done. Which contract type is MOST appropriate, and who bears the cost risk?
Explanation: When scope is too uncertain for the seller to price the work, a cost-reimbursable contract is appropriate: the seller is reimbursed for actual costs plus a fee, and the buyer bears the cost risk. No seller would accept a fixed price for work they cannot estimate — or if they did, they would price in a huge risk premium. Option D is wrong because a fixed price requires definable scope. Option B is wrong on the risk allocation: in T&M the buyer pays for what is actually used, so the seller does not bear the cost risk, and T&M is for smaller efforts rather than major uncertain work. Option A is wrong because FPIF is a fixed-price variant in which the seller bears the risk above the target cost, and it still requires enough scope definition to set a target price.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q3.A project manager needs a database specialist for three weeks, but the specialist's functional manager says the specialist is needed on another project at the same time. What should the project manager do FIRST?
Explanation: In a matrix organization, resources are negotiated, not commanded. The PMI reasoning chain is: understand the other party's constraints, then collaborate on a solution — perhaps the specialist can split their time, or the work can be sequenced differently, or the dates can shift. Option A is wrong because escalation is premature: the project manager should try to negotiate first. Option C is wrong because hiring externally is expensive and slow, and it should be a fallback, not a first move. Option D is wrong because assigning specialist work to someone without the skills risks quality and schedule problems, and it gives up on the negotiation before trying.
Exam objective: PMP ECO Task: Plan and manage resources (Process)
Q4.A team is confused about who has the final say on design decisions for a deliverable. The project manager decides to clarify roles using a RACI chart. How many people should be marked Accountable for the design decision?
Explanation: In a RACI chart, exactly one person is Accountable for each activity: the single person who owns the outcome and has the final say. Multiple people can be Responsible (doing the work), Consulted (giving input), or Informed (kept up to date), but accountability must rest with one person or nobody is truly accountable. Option A is wrong because two accountable people means neither is clearly in charge — the confusion the chart is meant to fix. Option D is wrong for the same reason: if everyone is accountable, no one is. Option C is wrong because shared accountability without a single owner is not accountability at all.
Exam objective: PMP ECO Task: Plan and manage resources (Process)
Q5.Three sellers submit bids for a contract. Seller A bids $80,000 with strong references and relevant experience. Seller B bids $78,000 with moderate experience. Seller C bids $45,000 with no relevant experience and no references. Which seller should the project manager select?
Explanation: Seller selection weighs multiple criteria: technical capability, past performance, experience, and references, as well as price. Seller A has the strongest profile, and the $2,000 saving from Seller B does not outweigh the difference in experience. Seller C's bid is less than 60% of the others with no relevant experience and no references — a classic warning sign that the seller does not understand the work, which usually ends in poor delivery, disputes, or abandonment. Option A and option B are both wrong because the lowest bid is not automatically the best bid. Option C is wrong because it treats the decision as a price comparison between two similar bids, ignoring that Seller A is the stronger candidate.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q6.During a phone call, a buyer and a seller agree to add extra work to an existing contract. The seller completes the extra work and invoices for it, but the buyer refuses to pay, saying the change was never approved. Who is right?
Explanation: Contract changes must be made through the contract change control process and agreed in writing by both parties. A verbal agreement during a phone call does not change the contract, so the buyer is not obliged to pay for the extra work — although the situation is a mess that better process would have prevented. Option A is wrong because verbal agreements are not binding for contract changes. Option D is wrong because completing work without an approved change does not create an obligation to pay for it. Option B is wrong because contract changes absolutely need approval — that is the point of contract change control.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q7.A seller is consistently delivering work late and below the quality standard in the contract. What should the project manager do FIRST?
Explanation: The PMI reasoning chain is the same for sellers as for team members: understand the problem, discuss it, and work toward a resolution within the terms of the agreement. The project manager reviews the contract (what are the performance standards, what remedies exist?), meets with the seller to discuss the issues, and agrees on corrective action with a timeline. Option A is wrong because termination is a last resort, not a first step, and it may itself breach the contract if the proper process is not followed. Option C is wrong because withholding payment unilaterally may breach the buyer's obligations and escalates the dispute. Option B is wrong because hiring a replacement in secret breaches the contract and guarantees a legal dispute.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q8.A project needs a component that is core to the organization's competitive advantage and involves proprietary technology. The project manager is deciding whether to make it in-house or buy it from a seller. What is the MOST important factor in this decision?
Explanation: Make-or-buy analysis weighs cost, capability, control, risk, and strategic importance — and for a component that is core to competitive advantage and involves proprietary technology, control and strategic importance dominate. Buying it would mean sharing proprietary technology with an outside party and depending on them for a core capability. Option B is wrong because short-term cost is only one factor, and it is outweighed here by the strategic risk. Option A is wrong because speed matters less than protecting the organization's core capability. Option C is wrong because the seller's reputation does not solve the fundamental problem of outsourcing a core, proprietary capability.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)