PMP PMP Mock Test
50 timed questions · 67 minutes · scored by domain, with re-study links for your weakest areas.
How it works: the timer starts as soon as this page loads. Answer each question, use the numbered dots to jump around, and flag questions to come back to. You see no feedback until you submit — just like the real exam. The pass guide is 70%: note that some vendors (including AWS) use scaled scoring and do not publish a percentage pass mark, so 70% is a study guide only.
Q1.A project manager is forming a new team from members of three different departments. In the first week, team members are polite but reluctant to share opinions, and decisions take a long time because nobody wants to disagree. What should the project manager do?
Explanation: This is the forming stage: the team does not yet trust each other enough to disagree openly. The leader's job is to deliberately create psychological safety — inviting opinions, rewarding people who raise concerns, and modelling openness by admitting uncertainty. Option A is wrong because deciding alone prevents the team from developing and creates dependency. Option C is wrong because quiet team members may have the best insights; the problem is the environment, not the people. Option D is wrong because avoiding meetings delays the trust-building the team needs.
Exam objective: PMP ECO Task: Lead the project team (People)
Q2.A team member tells the project manager privately that they are struggling with the workload and considering leaving the project. What should the project manager do FIRST?
Explanation: The PMI reasoning chain is: understand first, then act. Listening reveals what is actually causing the pressure — it may be the volume of work, unclear priorities, a skills gap, or a personal issue — and the response depends on the cause. Working together on an adjustment (reprioritizing, redistributing, providing support) keeps a valued team member and addresses the problem. Option B is wrong because dismissing the concern guarantees the team member will leave. Option D is wrong because reporting the person before trying to help them breaks trust. Option C is wrong because reassigning all their work without discussion signals that they are not valued and does not address the cause.
Exam objective: PMP ECO Task: Lead the project team (People)
Q3.Two team members disagree about which database technology to use. Both have valid technical arguments, and the decision will affect the project for years. The project manager has time to resolve this properly. Which conflict resolution style is BEST?
Explanation: When the issue matters, time is available, and both sides have valid arguments, collaboration is the right style: evaluate both technologies against the actual requirements (performance, cost, maintainability, team expertise) with both team members involved, and agree on the best solution. The decision will affect the project for years, so it deserves the best analysis, not the fastest resolution. Option B is wrong because forcing a decision on a long-lasting technical choice damages trust and may pick the worse technology. Option D is wrong because postponing a decision that blocks the design wastes time. Option C is wrong because agreeing with the loudest arguer is not a decision method — it rewards volume over merit.
Exam objective: PMP ECO Task: Manage conflicts (People)
Q4.A project manager and a vendor disagree about the interpretation of a contract clause. The project manager believes the vendor's interpretation would add $50,000 to the project cost. The contract is ambiguous on this point. What should the project manager do FIRST?
Explanation: The PMI reasoning chain is: understand first, then resolve collaboratively. Reviewing the contract documents establishes the facts, and discussing the clause with the vendor may reveal a shared interpretation or a compromise — the ambiguity may be resolvable once both sides explain their reading. Option C is wrong because threats escalate a disagreement that may be a genuine misunderstanding. Option B is wrong because paying $50,000 without establishing whether it is owed wastes project funds. Option D is wrong because escalation is premature — the project manager should first try to resolve the issue directly with the vendor.
Exam objective: PMP ECO Task: Manage conflicts (People)
Q5.A sponsor tells the project manager that they feel out of touch with the project and have been surprised by recent decisions. What should the project manager do?
Explanation: The sponsor's engagement needs are not being met, and the fix is to review the engagement approach with them: what information do they need, how often, and in what format? A sponsor who feels surprised needs better-targeted communication, not more communication. Option C is wrong because flooding the sponsor with every email creates overload and does not ensure they see what matters. Option D is wrong because dismissing the sponsor's concern damages the relationship and ignores their legitimate need to stay informed. Option A is wrong because inviting the sponsor to every team meeting wastes their time and changes the team dynamic.
Exam objective: PMP ECO Task: Manage stakeholder expectations (People)
Q6.A project will change the way a hospital's nursing staff record patient data. The nurses are key stakeholders with high interest in the project but limited formal power over it. How should the project manager engage them?
Explanation: On the power/interest grid, low-power, high-interest stakeholders are kept informed: regular communication so they feel heard, plus involvement in the work that affects them. The nurses will use the new system every day, so involving them in designing the process is both good engagement and good design — they know the current workflow better than anyone. Option B (manage closely) is for high-power, high-interest stakeholders. Option C (keep satisfied) is for high-power, low-interest stakeholders. Option A (monitor) is for low-power, low-interest stakeholders — and the nurses' high interest makes minimal contact inappropriate.
Exam objective: PMP ECO Task: Engage stakeholders (People)
Q7.A project team is spread across four countries. Team members report that important decisions made in meetings are often misunderstood by people who were not present. What should the project manager do?
Explanation: When decisions are misunderstood by people who were not present, the fix is to close the communication loop: document decisions in writing, distribute them promptly to everyone affected, and confirm understanding (for example, by asking recipients to acknowledge or summarize). This is basic communications management for distributed teams. Option C is wrong because more meetings do not fix the problem for people in other time zones, and they add to the meeting burden. Option D is wrong because email decisions are slower and less interactive than meeting decisions — the problem is not where decisions are made, but how they are communicated. Option A is wrong because forcing the same working hours across four countries is impractical and ignores the real issue.
Exam objective: PMP ECO Task: Plan and manage communication (People)
Q8.A project manager is developing the project management plan. A stakeholder asks why the plan includes subsidiary plans for scope, schedule, cost, quality, resources, communications, risk, procurement, and stakeholders instead of a single short document. What is the BEST explanation?
Explanation: The project management plan is integrated: it brings together the subsidiary plans so that a decision in one area is checked against its effects everywhere else. A schedule change affects cost; a scope change affects risk; a resource change affects quality. The subsidiary plans make those connections explicit and manageable. Option D is wrong because PMI does not mandate a fixed number of plans for every project — the plan is tailored to the project's size and complexity. Option A is wrong because small projects still need to manage each area, even if the plans are shorter. Option C is wrong because the plans directly shape how the team works — they are working documents, not sponsor paperwork.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q9.A project network has activities with the following durations: A (3 days) -> B (4 days) -> D (5 days) -> F (2 days), and A (3 days) -> C (2 days) -> E (6 days) -> F (2 days). Activity C also feeds into D. What is the project duration, and which path is critical?
Explanation: The paths are: A-B-D-F = 3 + 4 + 5 + 2 = 14 days; A-C-D-F = 3 + 2 + 5 + 2 = 12 days; A-C-E-F = 3 + 2 + 6 + 2 = 13 days. The longest path is A-B-D-F at 14 days, so it is the critical path and 14 days is the project duration. Option A (12 days) is the shortest path, not the longest. Option C (13 days) is the second-longest path. Option D has the right path but the wrong duration — 14 days, not 16.
Exam objective: PMP ECO Task: Plan and manage schedule (Process)
Q10.A project manager wants to shorten the project schedule. The critical path is 40 days. A non-critical activity with 10 days of float takes 15 days. If the project manager shortens the non-critical activity by 5 days, what happens to the project duration?
Explanation: Only work on the critical path affects the project duration. Shortening a non-critical activity by 5 days increases its float from 10 days to 15 days, but the critical path — and therefore the project duration — stays at 40 days. Option A is wrong because it assumes any time saved shortens the project. Option C is wrong for the same reason, and it double-counts the saving. Option D is wrong because shortening an activity cannot increase the project duration; using up float by delaying an activity is a different scenario.
Exam objective: PMP ECO Task: Plan and manage schedule (Process)
Q11.A project has a planned value (PV) of $200,000, an earned value (EV) of $150,000, and an actual cost (AC) of $180,000. What are the CPI and SPI?
Explanation: CPI = EV / AC = $150,000 / $180,000 = 0.83 (over budget). SPI = EV / PV = $150,000 / $200,000 = 0.75 (behind schedule). Option A inverts both ratios (AC / EV and PV / EV). Option D swaps the two indices: 0.75 is the SPI, not the CPI. Option B inverts and swaps them.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q12.A project's EAC is $550,000 and its BAC is $500,000. The project manager reports a VAC of -$50,000. What does this mean?
Explanation: VAC = BAC - EAC = $500,000 - $550,000 = -$50,000. A negative variance at completion means the project is forecast to finish over budget — by $50,000 in this case. Option C reverses the sign: a positive VAC would mean finishing under budget. Option D confuses VAC (a forecast of the final outcome) with CV (the current cost variance, EV - AC). Option A is wrong because VAC does not determine the management reserve, which is for unforeseen work, not for forecast overruns.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q13.A project team is finding many defects during final testing, and fixing them is delaying delivery. The project manager wants to reduce defects in the next phase. Which action is MOST aligned with PMI's quality approach?
Explanation: PMI's quality principle is prevention over inspection: defects caught during development (through peer reviews and automated tests) are far cheaper to fix than defects found in final testing. Building quality into the process addresses the root cause. Option C is wrong because more testers at the end find defects later, when they are most expensive to fix. Option A is wrong because reducing features to reduce defects sacrifices value instead of improving quality. Option D is wrong because extending testing accepts that defects will be created and merely gives more time to find them.
Exam objective: PMP ECO Task: Plan and optimize quality of products/deliverables (Process)
Q14.A project needs to hire a consulting firm for a well-defined six-week analysis task. The scope is clear, the deliverables are specified, and several firms can do the work. Which contract type is MOST appropriate?
Explanation: Well-defined scope with specified deliverables and multiple capable sellers is the textbook case for a firm fixed price contract: the seller can price the work accurately, the buyer knows the total cost in advance, and the seller bears the cost risk. Option C is wrong because cost-reimbursable contracts are for uncertain scope, where the seller cannot price the work — the opposite of this situation. Option B is wrong because T&M leaves the total cost open-ended when a fixed price was available; short duration alone does not make T&M the best choice. Option A is wrong because CPAF is a cost-reimbursable contract with a subjective award fee — again the wrong risk allocation for defined scope.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q15.A project is nearing completion. The project manager is preparing for closure. Which activity should be completed FIRST?
Explanation: Closure begins with verifying that all deliverables are complete and formally accepted by the customer or sponsor — everything else (releasing the team, archiving documents, celebrating) depends on that verification. If a deliverable is not accepted, there is still work to do. Option A is wrong because releasing the team before acceptance leaves nobody to fix problems if acceptance fails. Option B is wrong because archiving happens after the work is verified complete. Option D is wrong because celebrating before acceptance is premature — though celebrating after successful closure is exactly what a good project manager does.
Exam objective: PMP ECO Task: Manage project closure (Process)
Q16.A project manager is asked to approve a $200,000 scope change. The governance framework gives the project manager authority over changes up to $50,000; larger changes require steering committee approval. The sponsor is pressuring the project manager to approve it quickly. What should the project manager do?
Explanation: The change exceeds the project manager's authority, so it must go to the steering committee — and sponsor pressure does not change the governance framework. The project manager assesses the impact, submits the change to the committee, and explains the process to the sponsor. Option A is wrong because approving beyond your authority violates governance, even when the sponsor asks. Option C is wrong because refusing outright denies the committee the opportunity to decide — the change might be worthwhile. Option D is wrong because splitting a change to stay under an approval threshold is a deliberate evasion of the control process.
Exam objective: PMP ECO Task: Define and establish project governance (Business Environment)
Q17.A project manager is analyzing a risk with a 20% probability of occurring and an impact of $50,000 if it occurs. A mitigation action costing $4,000 would reduce the probability to 5%. Is the mitigation worth it, based on EMV?
Explanation: Before mitigation, EMV = 0.20 x $50,000 = $10,000. After mitigation, EMV = 0.05 x $50,000 = $2,500. The mitigation reduces expected cost by $7,500 for an investment of $4,000 — a net expected saving of $3,500, so it is worth it. Option C is wrong because EMV analysis accounts for the probability; the fact that the risk may not occur is already reflected in the calculation. Option D is wrong because a remaining EMV of $2,500 does not make the mitigation worthless — the question is whether the reduction exceeds the cost, and it does. Option A is wrong because not all risks should be mitigated regardless of cost; mitigation is justified when the expected benefit exceeds the cost.
Exam objective: PMP ECO Task: Plan and manage risk (Business Environment)
Q18.A risk owner reports that a high-priority risk's probability has increased from 30% to 70% because of a supplier's financial difficulties. What should the project manager do?
Explanation: Risk monitoring is continuous: when a risk's probability or impact changes, the risk register must be updated, the priority reassessed, and the response reviewed — a response designed for a 30% probability risk may be inadequate at 70%. The project manager might strengthen the mitigation, prepare a contingency plan, or consider avoidance. Option D is wrong because an outdated assessment leads to an inadequate response. Option C is wrong because the risk has not yet occurred — it is still a risk, not an issue, even at 70% probability. Option A is wrong because the risk cannot be transferred to the supplier whose financial difficulty is the cause of the risk.
Exam objective: PMP ECO Task: Plan and manage risk (Business Environment)
Q19.A customer submits a change request by email, asking for a feature that would delay the project by one month. The project manager believes the feature is valuable. What should the project manager do?
Explanation: Even a valuable change must go through integrated change control: document the request, assess the full impact (one month's delay, plus cost, risk, and resource effects), and let the authorized decision-maker decide. The project manager's belief that the feature is valuable is a recommendation, not an approval. Option D is wrong because implementing before approval is scope creep, however valuable the feature. Option B is wrong because refusing outright denies the decision-maker the chance to weigh the feature's value against the delay. Option C is wrong because adding work without formal approval bypasses change control.
Exam objective: PMP ECO Task: Manage and control changes (Business Environment)
Q20.A project team has been delivering software in two-week sprints. At the retrospective, the team suggests that daily standup meetings are taking too long and should be limited to 10 minutes with a strict format. What should the project manager do?
Explanation: Continuous improvement works through small, team-owned experiments: try the change, measure the result, and keep it if it works. The team's suggestion is specific and testable, and the next retrospective is the natural point to review it. Option D is wrong because standard practices should be adapted to the team's needs — agile values responding to the team's experience over following a rigid formula. Option A is wrong because cancelling standups removes the team's daily coordination entirely, which is a much bigger change than the team suggested. Option C is wrong because the team should own its working agreements; the project manager facilitates improvement, not dictates it.
Exam objective: PMP ECO Task: Continuous improvement (Business Environment)
Q21.A project manager notices that a senior developer has become quiet in meetings, misses two deadlines, and seems disengaged. The project manager has not spoken to the developer about this yet. What should the project manager do FIRST?
Explanation: The PMI reasoning chain is: understand before you act. A change in behavior has a cause — it could be a personal issue, a conflict with a colleague, unclear requirements, or burnout — and the project manager cannot choose the right response until they know what it is. A private conversation is the servant-leader first step: it shows respect, builds trust, and gathers the facts. Option A is wrong because escalation is a later step, taken only after the project manager has tried to resolve the issue directly. Option B treats the symptom (missed work) while ignoring the person, and it signals to the team that struggling members get sidelined. Option C jumps to discipline before understanding, which is the opposite of the PMI mindset and would damage trust.
Exam objective: PMP ECO Task: Lead the project team (People)
Q22.A project team has been working together for three months but team members still seem to pull in different directions, and two members have said they do not see the point of the project. What is the BEST action for the project manager?
Explanation: When people pull in different directions and cannot see the point of the project, the missing ingredient is a shared vision — a common understanding of why the project exists and what success looks like. The vision must be developed WITH the team, because people commit to a vision they helped create and merely comply with one handed to them. Option D is wrong because schedule pressure does not create purpose; it creates stress. Option B is wrong because it treats a leadership failure (no shared vision) as a staffing problem, and replacing people does not fix the underlying issue. Option A is weaker than B: a sponsor message is one-way communication, and it does not create the team's own shared understanding.
Exam objective: PMP ECO Task: Develop a common vision (People)
Q23.A sponsor demands that the team work weekends for the next month to recover a two-week schedule slip. The team has already been working long hours and two members have mentioned burnout. What should the project manager do?
Explanation: A servant leader protects the team from unsustainable demands while still working transparently with the sponsor on realistic alternatives. The reasoning chain is: (1) the team is already showing burnout, so more overtime will reduce quality and cause more delays; (2) the schedule problem has other solutions — reprioritizing scope, adjusting the deadline, or adding resources; (3) the project manager's job is to bring the sponsor and the team together on one of those options. Option D is wrong because passing on an unreasonable demand without challenge is not leadership, and it will damage the team. Option C is wrong because flat refusal without offering alternatives is unprofessional and ignores the sponsor's legitimate concern. Option B is wrong because it accepts the unsustainable pace and offers compensation later, which does not prevent burnout now.
Exam objective: PMP ECO Task: Lead the project team (People)
Q24.Two senior engineers disagree strongly about the technical design of a key component. Each believes their approach is better, and the argument is delaying the project. What is the BEST approach for the project manager?
Explanation: This is a task conflict between two people with legitimate technical views, and the PMI-preferred style is collaborate/problem-solve: bring the parties together, evaluate both approaches against the actual requirements, and agree on the best solution. The reasoning chain is: understand both positions and their underlying interests, use facts (the requirements) as the judge, and reach a solution both can support. Option C is force/direct — it may be fast, but it damages trust and may pick the worse design. Option B is a false compromise that creates an incoherent design and doubles the work. Option A is withdraw/avoid — the decision is blocking the project, so delaying it makes the problem worse.
Exam objective: PMP ECO Task: Manage conflicts (People)
Q25.A team member repeatedly interrupts colleagues in meetings, dismisses their ideas with personal insults, and has caused two colleagues to ask to leave the project. What should the project manager do?
Explanation: This is a conduct issue, not a conflict to be facilitated: personal insults and behavior that drives people off the project violate basic respect and organizational norms. The correct response is to address the behavior directly and privately, document the conversation, and involve human resources or the proper process if the behavior continues. Option A is wrong because facilitating a group discussion about misconduct puts the victims on the spot and treats abuse as a difference of opinion. Option C is wrong because technical skill never excuses behavior that harms the team. Option D is wrong because waiting for a retrospective leaves the harmful behavior unaddressed for weeks while more damage is done.
Exam objective: PMP ECO Task: Manage conflicts (People)
Q26.During project execution, a department head who was not identified as a stakeholder objects to a deliverable and threatens to block its rollout. What should the project manager do FIRST?
Explanation: The PMI reasoning chain is: understand first, then update the plan. A stakeholder who appears late is a common reality, not a rule violation — stakeholder identification continues throughout the project. Meeting them reveals what they actually object to (which may be fixable), and updating the register and engagement plan prevents the same surprise from recurring. Option C is wrong because telling a stakeholder they do not count is the fastest way to turn an objection into active opposition. Option B is wrong because escalation is premature — the project manager has not yet tried to understand or resolve the concern. Option D is wrong because rolling out over a stakeholder's objection creates a bigger problem than the delay it avoids.
Exam objective: PMP ECO Task: Engage stakeholders (People)
Q27.A key stakeholder tells the project manager they expected the new system to include automated reporting, but automated reporting was never in the project scope. What should the project manager do?
Explanation: The reasoning chain is: align expectations against the documented scope, then use the proper process for any change. Reviewing the scope documents together shows the stakeholder what was agreed (their expectation may be based on a genuine misunderstanding), and change control ensures that adding the feature is assessed for its impact on schedule, cost, and risk before anyone commits to it. Option A is scope creep: an uncontrolled addition that consumes time and budget without assessment. Option B is wrong because dismissing the stakeholder without discussion damages the relationship and leaves the expectation unaddressed. Option D is also scope creep, made worse by hiding it from the documentation.
Exam objective: PMP ECO Task: Align stakeholder expectations (People)
Q28.Using the stakeholder engagement assessment matrix, a project manager finds that the operations manager is currently RESISTANT to the project but needs to be SUPPORTIVE for the rollout to succeed. What is the BEST action?
Explanation: The gap between current (resistant) and desired (supportive) engagement is the work to be done, and the first step is understanding why the stakeholder is resistant — they are usually protecting something, such as their team's workload, their budget, or their current way of working. Once the project manager understands the concern, they can address it with information, involvement, or adjustments to the plan. Option B is wrong because excluding a resistant stakeholder confirms their worst fears and guarantees opposition at rollout. Option D is wrong because an instruction from the sponsor produces compliance at best, not genuine support, and it bypasses the real issue. Option A is wrong because the matrix exists precisely to drive engagement actions — recording a gap without acting on it defeats its purpose.
Exam objective: PMP ECO Task: Engage stakeholders (People)
Q29.A project has 8 stakeholders who all need to communicate with each other. Two more stakeholders join the project. How many communication channels are there now?
Explanation: The communication channels formula is n(n-1)/2, where n is the number of people. With the two new stakeholders, n = 10, so the channels are 10 x 9 / 2 = 45. Option B (36) is the result for 9 people (9 x 8 / 2 = 36) — it counts only one of the two new stakeholders. Option D (28) is the number of channels before the new stakeholders joined (8 x 7 / 2 = 28). Option C (90) is the result of forgetting to divide by 2 (10 x 9 = 90).
Exam objective: PMP ECO Task: Plan and manage communication (People)
Q30.A project manager must inform a key stakeholder that the project will be delayed by six weeks. What is the BEST way to deliver this news?
Explanation: Bad news about a significant delay is sensitive and complex: the stakeholder will have questions, concerns, and possibly strong feelings, and the project manager needs to read their reaction and respond in real time. Interactive communication — face to face or by video — is the right method. Option D is wrong because email cannot handle the stakeholder's reaction, and important news delivered by email often reads as evasive. Option B is wrong because posting bad news on a shared page is impersonal and denies the stakeholder a chance to discuss it. Option C is wrong because withholding bad news for two weeks destroys trust; stakeholders should hear about problems from the project manager, promptly, not discover them later.
Exam objective: PMP ECO Task: Plan and manage communication (People)
Q31.A project manager discovers that a deliverable will be two weeks late. Before deciding what to do, what should the project manager do FIRST?
Explanation: The PMI reasoning chain is: assess before you act, and assess the whole project, not one dimension. A two-week delay to one deliverable may or may not affect the project's end date (it depends on whether the deliverable is on the critical path), and the right response depends on the full impact — on cost, on dependent work, on stakeholders. Only after that assessment can the project manager choose between options such as overtime, scope adjustment, or a change request. Option C is wrong because changing the baseline is a formal change-control decision, not something the project manager does unilaterally as a first step. Option A is wrong because overtime is a response chosen before the impact is understood, and it may be unnecessary or harmful. Option D is wrong because removing scope is a major decision that needs the same impact assessment first.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q32.A customer asks for a new feature that would add three weeks to the schedule and $40,000 to the cost. The project manager has confirmed the estimates. What should the project manager do NEXT?
Explanation: A change that affects scope, schedule, and cost must go through integrated change control: a formal change request is submitted, its impact is assessed, and it is approved (or rejected) by the authorized decision-maker before any work begins. This protects the baselines and ensures the customer understands the trade-off they are asking for. Option A is wrong because adding scope without approval is scope creep, even when the customer asked for it. Option B is wrong because refusing outright ignores the possibility that the feature is worth the cost — the change process exists to make that decision properly. Option C is wrong because hidden work is still scope creep, and it creates undocumented, untested, and unbudgeted deliverables.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q33.A project network has three paths from start to finish: Path A-B-D-F takes 14 days, Path A-C-D-F takes 12 days, and Path A-C-E-F takes 13 days. What is the critical path, and what is the float on activity E?
Explanation: The critical path is the longest path through the network: A-B-D-F at 14 days determines the project duration. Activity E is on path A-C-E-F, which takes 13 days — one day shorter than the critical path — so activity E has 1 day of float: it can be delayed by one day before its path becomes critical. Option B is wrong because A-C-E-F (13 days) is not the longest path. Option A is wrong because E is not on the critical path, so its float is not zero. Option D is wrong because A-C-D-F (12 days) is the shortest path, not the critical path.
Exam objective: PMP ECO Task: Plan and manage schedule (Process)
Q34.A project is two weeks behind schedule and the sponsor will not approve additional budget. The project manager wants to recover the schedule without spending more money. Which technique should the project manager try FIRST?
Explanation: Fast tracking overlaps sequential activities on the critical path so they run in parallel. It costs little or no extra money, which fits the sponsor's budget constraint, though it adds risk because work starts before its predecessor is complete. The exam's rule is to fast track first, then crash if more compression is needed. Option A is wrong because crashing adds resources and therefore costs money, which the sponsor has ruled out. Option B is wrong because resource leveling resolves resource over-allocation and can extend the schedule — it does not compress it. Option D is wrong because reducing scope without the sponsor's knowledge breaks the baseline and the change control process.
Exam objective: PMP ECO Task: Plan and manage schedule (Process)
Q35.A project has a planned value (PV) of $100,000, an earned value (EV) of $80,000, and an actual cost (AC) of $90,000. What are the cost variance (CV) and schedule variance (SV)?
Explanation: CV = EV - AC = $80,000 - $90,000 = -$10,000. A negative cost variance means the project is over budget. SV = EV - PV = $80,000 - $100,000 = -$20,000. A negative schedule variance means the project is behind schedule. Option C has both signs wrong — it computes AC - EV and PV - EV instead. Option B swaps the two variances: -$20,000 is the schedule variance, not the cost variance. Option D gets the cost variance right but the schedule variance wrong — EV is less than PV, so the project is behind, not ahead.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q36.A project has an earned value (EV) of $80,000 and an actual cost (AC) of $90,000. The budget at completion (BAC) is $500,000. If the project continues at its current cost performance, what is the estimate at completion (EAC)?
Explanation: When future work is expected to continue at the current cost performance, EAC = BAC / CPI. First, CPI = EV / AC = $80,000 / $90,000 = 0.8889. Then EAC = $500,000 / 0.8889 = $562,500. Option D ($510,000) is the result of using EAC = AC + (BAC - EV) = $90,000 + $420,000 = $510,000 — the formula for a one-off variance, which is wrong here because the question says current performance will continue. Option B ($590,000) has no basis in any standard EAC formula. Option A ($500,000) is the BAC, which assumes the project will finish on budget despite running over budget so far.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q37.A project team keeps finding the same type of defect in testing. The project manager wants to identify the root cause of the defect. Which quality tool should be used?
Explanation: A cause-and-effect (fishbone or Ishikawa) diagram is the tool for root-cause analysis: it organizes possible causes of a problem into categories (people, process, materials, environment, and so on) so the team can work through them systematically and find the underlying cause. Option C is wrong because a Pareto chart ranks defect types by frequency — useful for deciding which defect to fix first, but it does not find the cause of a specific defect. Option A is wrong because a control chart shows whether a process is stable over time, not why a defect occurs. Option D is wrong because a scatter diagram shows whether two variables are related, which is a different question from root cause.
Exam objective: PMP ECO Task: Plan and optimize quality of products/deliverables (Process)
Q38.A project manager audits the team's development process and finds that the team is not following the agreed code-review procedure. Which quality process is the project manager performing?
Explanation: Manage quality (quality assurance) is about the process: auditing whether the project is following the right processes and standards. Checking whether the team follows the agreed code-review procedure is a process audit, so it is manage quality. Option B is wrong because control quality inspects deliverables (the product), not processes — testing the code itself would be control quality. Option A is wrong because plan quality management happens during planning, when quality requirements and standards are defined. Option C is wrong because validate scope is the formal acceptance of completed deliverables by the customer, not a process audit.
Exam objective: PMP ECO Task: Plan and optimize quality of products/deliverables (Process)
Q39.A project needs a specialized component. The scope is well defined, the requirements are stable, and several sellers can supply it. Which contract type is MOST appropriate?
Explanation: When scope is well defined and requirements are stable, the seller can price the work accurately, so a firm fixed price contract is appropriate: the buyer knows the total cost in advance and the seller bears the cost risk. Option A is wrong because cost-reimbursable contracts are for uncertain scope — here the scope is certain, so there is no reason for the buyer to bear the cost risk. Option B is wrong because T&M is for small, short efforts or work that cannot be fully defined; it leaves the total cost open-ended when a fixed price was available. Option D is wrong because CPAF is a cost-reimbursable contract with a subjective award fee — again, the wrong risk allocation for well-defined scope.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q40.Three sellers submit bids for a contract. Seller A bids $80,000 with strong references and relevant experience. Seller B bids $78,000 with moderate experience. Seller C bids $45,000 with no relevant experience and no references. Which seller should the project manager select?
Explanation: Seller selection weighs multiple criteria: technical capability, past performance, experience, and references, as well as price. Seller A has the strongest profile, and the $2,000 saving from Seller B does not outweigh the difference in experience. Seller C's bid is less than 60% of the others with no relevant experience and no references — a classic warning sign that the seller does not understand the work, which usually ends in poor delivery, disputes, or abandonment. Option A and option B are both wrong because the lowest bid is not automatically the best bid. Option C is wrong because it treats the decision as a price comparison between two similar bids, ignoring that Seller A is the stronger candidate.
Exam objective: PMP ECO Task: Plan and manage procurement (Process)
Q41.A project manager discovers that the project is three weeks behind schedule and $30,000 over budget. The next status meeting with the sponsor is in two weeks. What should the project manager do?
Explanation: The PMI reasoning chain is: report bad news promptly, honestly, and with a plan. The sponsor needs to know now — not in two weeks — because the variance may affect decisions the sponsor is making today, and because the proposed response may need the sponsor's approval or support. Option A is wrong because waiting two weeks withholds information the sponsor needs. Option D is wrong because quiet recovery attempts hide the problem and, if they fail, the sponsor learns about a worse situation even later. Option B is wrong because falsifying a status report is dishonest and a serious breach of professional conduct.
Exam objective: PMP ECO Task: Evaluate project status (Process)
Q42.A project's funding is cut and the sponsor decides to cancel the project immediately. What should the project manager do?
Explanation: Early termination still requires proper project closure. The project manager documents what was completed, preserves the work products and the knowledge gained (lessons learned), closes contracts and settles obligations, and releases resources formally. This protects the organization's investment in the work done so far and ensures the knowledge is available to future projects. Option A is wrong because abandoning the project without documentation wastes everything that was built and learned. Option B is wrong because the sponsor has cancelled the project — continuing to spend is unauthorized. Option C is wrong because asking people to work unpaid is unethical and unprofessional.
Exam objective: PMP ECO Task: Manage project closure (Process)
Q43.A project is approaching a phase gate. The business case has weakened significantly since the project started, but the team has already spent 60% of the budget. What should happen at the gate?
Explanation: A phase gate is a governance decision point: the governance body reviews the project's performance and the current business case and decides whether to continue, continue with changes, or stop. Money already spent is a sunk cost — it should not drive the decision. What matters is whether the project will still deliver value from this point forward. Option C is wrong because it commits the sunk-cost fallacy: spending more on a project whose business case has failed wastes more money, not less. Option B is wrong because the continue/stop decision belongs to the governance body, not the project manager. Option A is wrong because skipping the gate removes the very oversight that exists to catch this situation.
Exam objective: PMP ECO Task: Define and establish project governance (Business Environment)
Q44.A team member suggests skipping a required safety inspection to recover two days on the schedule. The inspection is mandated by regulation. What should the project manager do?
Explanation: Compliance with a regulatory safety requirement is not negotiable and cannot be traded for schedule. The project manager must refuse, explain why — safety regulations exist to protect people, and breaching them exposes the organization to legal liability and people to harm — and then work on legitimate schedule recovery options such as fast tracking or crashing. Option B is wrong because it breaks the law and endangers people. Option C is wrong because documenting a bad decision does not make it acceptable. Option A is wrong because compliance is not a democratic decision — the team cannot vote to break a regulation.
Exam objective: PMP ECO Task: Plan and manage project compliance (Business Environment)
Q45.A project has identified a risk: there is a 30% probability that a key supplier will fail, which would cost the project $20,000. What is the expected monetary value (EMV) of this risk?
Explanation: EMV = probability x impact = 0.30 x $20,000 = $6,000. Because this is a threat (a negative risk), the EMV is a $6,000 expected cost. Option D ($14,000) is the result of multiplying by 70% (the probability the risk does not occur), which is not how EMV works. Option B ($20,000) is the full impact, ignoring the probability. Option A ($26,000) has no basis in the EMV formula.
Exam objective: PMP ECO Task: Plan and manage risk (Business Environment)
Q46.A construction project faces the risk of damage from severe weather. The project manager buys insurance to cover weather-related damage. Which risk response strategy is this?
Explanation: Buying insurance is the classic example of transfer: the risk itself (severe weather) still exists, but the financial impact is shifted to a third party (the insurer) in exchange for a premium. Option A is wrong because insurance does not reduce the probability of bad weather or the physical damage — it only changes who pays for it. Option D is wrong because the risk is not eliminated. Option B is wrong because escalation means raising a risk to a higher level within the organization, not buying a service from an external party.
Exam objective: PMP ECO Task: Plan and manage risk (Business Environment)
Q47.A stakeholder asks the project manager to add a new report to the project. The project manager estimates the report will take one week to build. What should the project manager do NEXT?
Explanation: Every change — even a small one — goes through integrated change control: the request is documented, its full impact is assessed (one week of building may also mean testing, documentation, training, and maintenance), and it is approved by the authorized decision-maker before work begins. Option B is wrong because implementing before approval is scope creep, regardless of the size of the change. Option C is wrong because refusing outright ignores the possibility that the report is genuinely valuable — the change process exists to make that decision properly. Option A is wrong because hidden work is scope creep, and it creates undocumented, untested deliverables.
Exam objective: PMP ECO Task: Manage and control changes (Business Environment)
Q48.A key supplier has gone bankrupt and can no longer deliver materials the project needs next week. The risk register listed supplier failure as a risk, but no response was planned. What should the project manager do FIRST?
Explanation: The supplier failure has already happened, so it is no longer a risk — it is an issue. The project manager should log it in the issue log, assess its impact on the schedule and cost, and take urgent action to find an alternative supplier. Option C is wrong because updating the risk register does not solve the problem; the event has moved from risk to issue, and it needs issue management. Option A is wrong because acceptance is a strategy for risks that have not yet occurred, not for problems that are already affecting the project. Option D is wrong because waiting wastes the time needed to find an alternative — materials are needed next week.
Exam objective: PMP ECO Task: Remove impediments and manage issues (Business Environment)
Q49.A competitor launches a product very similar to the one a project is building, six months before the project's planned launch. What should the project manager do FIRST?
Explanation: The PMI reasoning chain is: assess the external change, then escalate the business decision. A competitor's launch may or may not destroy the project's value — it depends on differentiation, market size, and timing — and the project manager must assess the impact on the business case before anyone decides what to do. The decision to continue, change, or stop belongs to the sponsor and governance. Option C is wrong because ignoring a major market change is not management — the project's value proposition may have changed fundamentally. Option B is wrong because cancelling is a governance decision, not the project manager's first response. Option A is wrong because cutting testing to rush a launch sacrifices quality and may produce a product that fails in the market.
Exam objective: PMP ECO Task: Evaluate external business environment changes (Business Environment)
Q50.A project will replace a manual process with an automated system. The employees who use the current process are anxious about the change and several have said they will not use the new system. What should the project manager do?
Explanation: Resistance to change is normal, and the PMI approach is to understand it and address it: communicate the reason for the change, involve the affected people in designing the transition, provide training so they feel competent with the new system, and listen to their concerns (which may reveal genuine problems with the plan). Option D is wrong because threats produce compliance at best and sabotage at worst — and they ignore the legitimate anxiety behind the resistance. Option A is wrong because ignored resistance does not go away; it grows until it blocks the change. Option B is wrong because cancelling a worthwhile project to avoid managing change is an abdication of leadership.
Exam objective: PMP ECO Task: Support organizational change (Business Environment)