Cost, Finance and Earned Value

PMP PMP · Process

By Abu Anns · Last updated 20 November 2026Exam version: July 2026 ECO (current since 9 July 2026)

Cost management in one picture

Cost management answers three questions: how much will the project cost (estimate costs), how much are we allowed to spend and when (determine budget), and are we on track (control costs). The July 2026 ECO gives the Process domain one task here: plan and manage finance. The exam tests cost management through concepts and through calculations, and the calculations center on one method: earned value management (EVM). EVM is the most formula-heavy topic on the PMP exam, and it is also one of the most predictable — the same small set of formulas appears in question after question, so learning them properly is one of the highest-return study investments you can make. Our EVM calculator page lets you practise every formula with your own numbers.

Estimating costs uses the same techniques as estimating durations: analogous (based on similar past projects), parametric (based on a statistical rate), bottom-up (detailed estimates rolled up from work packages), and three-point. Costs are estimated for all resources — people, materials, equipment, facilities, and services — and the estimates are rolled up into the cost baseline, the approved time-phased budget. The baseline includes the contingency reserve for known risks but not the management reserve for unforeseen work, which is held outside the baseline by the sponsor. The total project budget is the cost baseline plus the management reserve.

Earned value management: the three core values

EVM compares what you planned to spend, what you have actually earned, and what you have actually spent. It uses three core values, all measured in money:

ValueMeaningAlso called
Planned Value (PV)The budgeted cost of the work scheduled to be done by nowBCWS
Earned Value (EV)The budgeted cost of the work actually completed by nowBCWP
Actual Cost (AC)The real cost incurred for the work done so farACWP

From these three values come the variances and indices that tell you whether the project is on track. Cost variance (CV) = EV - AC: positive means under budget, negative means over budget. Schedule variance (SV) = EV - PV: positive means ahead of schedule, negative means behind. The cost performance index (CPI) = EV / AC: above 1.0 means under budget, below 1.0 means over budget. The schedule performance index (SPI) = EV / PI: above 1.0 means ahead of schedule, below 1.0 means behind. The exam's favorite trap is the direction of the comparison: for cost, you compare EV against AC (what you earned versus what you spent); for schedule, you compare EV against PV (what you earned versus what you planned to earn by now).

A worked example makes this concrete. Suppose PV = $100,000, EV = $80,000, and AC = $90,000. Then CV = 80,000 - 90,000 = -$10,000 (over budget by $10,000), SV = 80,000 - 100,000 = -$20,000 (behind schedule by $20,000 of work), CPI = 80,000 / 90,000 = 0.89 (getting 89 cents of value for every dollar spent), and SPI = 80,000 / 100,000 = 0.80 (progressing at 80% of the planned rate). This project is both over budget and behind schedule — and the exam will often ask you to interpret exactly this kind of combination.

Forecasting: EAC, ETC, VAC, and TCPI

EVM also forecasts where the project will end up. The budget at completion (BAC) is the total budget for the whole project. The estimate at completion (EAC) forecasts the total cost at the end, and there are four standard ways to calculate it, each appropriate in a different situation:

SituationEAC formula
Future work will be done at the planned rate (the variance was a one-off)EAC = AC + (BAC - EV)
Future work will continue at the current cost performanceEAC = BAC / CPI
Future work will be affected by both cost and schedule performanceEAC = AC + [(BAC - EV) / (CPI x SPI)]
A new bottom-up estimate is needed (the original estimate is no longer valid)EAC = AC + bottom-up ETC

The estimate to complete (ETC) is the forecast cost of the remaining work: ETC = EAC - AC. The variance at completion (VAC) is the forecast overrun or underrun: VAC = BAC - EAC (positive means the project is forecast to finish under budget). The to-complete performance index (TCPI) measures how efficiently the remaining work must be done to hit a target: TCPI = (BAC - EV) / (BAC - AC) to finish on the original budget, or (BAC - EV) / (EAC - AC) to finish on the revised forecast. A TCPI above 1.0 means the team must perform better than planned for the rest of the project — and a TCPI much above 1.1 is usually a sign that the target is unrealistic.

Using the worked example with BAC = $500,000: EAC = BAC / CPI = 500,000 / (80,000/90,000) = $562,500 (assuming current cost performance continues), ETC = 562,500 - 90,000 = $472,500 still to spend, VAC = 500,000 - 562,500 = -$62,500 (forecast to finish $62,500 over budget), and TCPI = (500,000 - 80,000) / (500,000 - 90,000) = 420,000 / 410,000 = 1.02 — the team would need to perform at 102% efficiency to finish on budget, which is demanding but not impossible.

Controlling costs: what the numbers mean for action

The exam does not just ask you to calculate EVM figures; it asks what to do about them. The reasoning chain is the same as everywhere else in the Process domain: understand the cause of the variance before choosing a response. A cost overrun caused by a one-off event (a supplier's price increase that will not recur) calls for a different response than a systematic overrun (the team consistently working slower than estimated). The first case suggests EAC = AC + (BAC - EV), because future work will proceed at the planned rate; the second suggests EAC = BAC / CPI, because current performance will continue. A question that describes the cause of a variance and asks which EAC formula to use is testing exactly this judgment.

Common responses to a cost overrun include reducing scope (through change control), finding cheaper resources, improving efficiency, and re-baselining the budget if the original estimate is no longer valid. What the project manager does not do is hide the overrun, cut quality to save money without approval, or spend from the management reserve without the sponsor. Cost control is also where the exam tests funding: projects are funded in stages, and the project manager must ensure that spending stays within the funding limits for each period, not just within the total budget.

Financial concepts the exam touches

Beyond EVM, the exam tests a small set of financial ideas, mostly in the context of project selection and business value. Return on investment (ROI) measures the return relative to the cost. Net present value (NPV) discounts future cash flows to today's value — a higher NPV is better, and a negative NPV means the project destroys value. Internal rate of return (IRR) is the discount rate at which NPV equals zero — a higher IRR is better. Payback period is how long it takes for the project to recover its investment — shorter is better. Benefit-cost ratio (BCR) divides benefits by costs — above 1.0 means benefits exceed costs. The exam rarely asks for calculations of these (beyond simple cases), but it does ask you to choose between projects using them: given two projects, the one with the higher NPV is usually the better investment, and a project with a BCR below 1.0 should not be selected.

Exam mindset for cost and finance

For cost questions, learn the EVM formulas until they are automatic, and always check the direction of your comparisons: EV minus AC for cost, EV minus PV for schedule, EV divided by AC for CPI, EV divided by PV for SPI. When a question asks for a forecast, read the scenario for the cause of the variance — it tells you which EAC formula to use. And remember that numbers drive decisions: a CPI below 1.0 is not just a number, it is a signal to investigate, to forecast honestly, and to act through the proper process.

Advertisement

Exam traps to watch for

Practice questions

Test yourself on this guide. Answers are checked instantly, with a full explanation for each question.

Q1.A project has a planned value (PV) of $100,000, an earned value (EV) of $80,000, and an actual cost (AC) of $90,000. What are the cost variance (CV) and schedule variance (SV)?

Report an error

Q2.A project has an earned value (EV) of $80,000 and an actual cost (AC) of $90,000. The budget at completion (BAC) is $500,000. If the project continues at its current cost performance, what is the estimate at completion (EAC)?

Report an error

Q3.A project is over budget because of a one-time supplier price increase that will not recur. The project manager wants to forecast the total cost at completion. Which EAC formula should be used?

Report an error

Q4.A project has a CPI of 0.85 and an SPI of 1.10. What does this mean?

Report an error

Q5.A project has a BAC of $200,000, an EV of $120,000, and an AC of $100,000. What is the to-complete performance index (TCPI) to finish on the original budget?

Report an error

Q6.A project manager reports a CPI of 0.75 to the sponsor. The sponsor asks what the project manager will do about it. What is the BEST response?

Report an error

Q7.A project's cost baseline is $400,000 and the management reserve is $50,000. What is the total project budget?

Report an error